PROGRESS OF THE PROJECT
Creating something new with far-sighted planning: Planning a new use for the former mining site started at an early stage to enable a new usage for the unique site as soon as possible. Since then, several milestones have been reached: From extensive feasibility studies to the establishment of a project company to the marketing of the site.
2013
AV 3/7 working group founded – with the city of Marl, Evonik, Logport Ruhr, RAG AG and RAG Montan Immobilien as members
November 2014
Permit notice for the funding of the feasibility study phase I
May 2015 – September 2015
Development of the feasibility study phase I with over a dozen experts
December 2015
After more than a century the mining site Auguste Victoria 3/7 closes, marking the end of coal mining at the site in Marl
2016
Beginning of phase II of the feasibility study
Withdrawal of the mining industry
Start of urban planning
2017
Preparation and approval of the restructuring plan
Resolution on the preparation of the development scheme
2018
Completion of phase II of the feasibility study
2019
Founding of the project enterprise gate.ruhr GmbH
Permit notice for the funding of the project by the State of NRW
2020
Beginning of implementation phase I
Marketing starts
2021
Implementation phase I
Further marketing